Here are some ideas for project status reports.
The 1 Pager
On this one I am trying to communicate all the important stuff on a single page.
At the top I’ve got how we are doing for time, money and scope. To the right I put any headlines or issues. I’ve got a risk section showing the problems we are facing and how we are addressing. Then the velocity and projected date on the right.
So at a glance I should be able to see whether we are in trouble (via the red, yellow, green stop light) and how we are trending on time, money, and scope.
The Burndown
Ah. My favorite graph – the burndown. The burndown never lies. It’s the story of your project. It shows you how you are trending. It can show where you need to be. It shows you changes in scope. It also tells you when you are in trouble.
Changes in Scope
Every project is different. On some scope management is easy and built around trust. On others you have to watch it like a hawk.
If I think scope management is going to be an issue on a project, I will make any changes to scope crystal clear with a slide like this:
Others
Every company is different. And sometimes I will create dedicated presentations if there is a really important message I need to deliver. But if you basically make everything visible, and ask yourself:
What would I like to see if it was my project?
you’ll probably come close to what your sponsor wants to see to.
Jul 22, 2014 @ 13:00:08
How did you create that stoplight in the top right corner?
Jul 22, 2014 @ 15:03:21
You mean the top left? Rectangle, x3 circles, and then fill in the colors of the shapes.
Sep 07, 2014 @ 05:49:35
Looks promising
Do you share the report template?
Sep 08, 2014 @ 04:32:07
I do. You can purchase a copy here (only $7).
http://www.agilenutshell.com/project_status_reports
Jun 02, 2015 @ 04:21:55
Hi JR,
I just purchased the project status report but got an error page saying “We’re sorry, but something went wrong.”
Can you provide me access to the video please?
Thanks,
Rod
Jun 03, 2015 @ 04:36:36
Yes – can do Rod. Unforrtunately I am out of the country and without my work laptop. I will be back in 2 weeks. I will setup you directly with the video at that point. So sorry for the inconvenience. Jonathan
Jun 17, 2015 @ 17:39:49
Hi Rod – I just checked and can’t see any payment coming through from you. So you shouldn’t have been charged anything. Please let me know if this isn’t the case.
Cheers – Jonathan
Jul 28, 2015 @ 15:13:46
HI JR,
I am looking for weekly scrum status report template ? Do you have anything or you can change if i need a change in above template ?
Jul 29, 2015 @ 04:19:55
Nothing beyond what you see here Rupin.
Cheers – Jonathan
Jul 31, 2015 @ 13:48:43
Thanks Jonathan
Jul 31, 2015 @ 13:54:04
I am trying to buy this report template but got an error page saying “We’re sorry, but something went wrong.” after enter cc information.
How can i get that ?
Aug 01, 2015 @ 05:19:22
Hmm – thats strange.
I am on holidays at the moment, but when I get back I will make sure you weren’t changed, and see if I can’t see what what wrong.
Sorry for the inconvenience Rupin. Will be back next week.
Cheers – Jonathan
What Are Project Milestones (And How To Use Them)
Sep 04, 2018 @ 07:02:39
Nov 21, 2018 @ 07:18:29
Hi,
Do you have project status reports with KPI and Risk Rating Matrix ?
Nov 22, 2018 @ 20:35:05
Hi Sarah,
It depends 🙂 If the team and management have agreed upon KPI that are important to the project, yes I would. Same with Risks.
Though risks I try not to bombard them with, and I really just put the big show stoppers up that need attention.
The reason being there are thousands of risks that could derail any project. But only a few we can do anything about and worth sweating.
Cheers – Jonathan
Oct 22, 2019 @ 13:28:45
Hi, the page contains only powerpoint presentation – not actual templates in xls. Could you please have look at it?
Thanks!
What Are Project Milestones (And How To Use Them)
Jun 18, 2021 @ 20:48:44